RAMSynapse
Log inSign up

Reliability Block Diagram · Chapter 3

The Method

How the analysis actually runs, step by step.

An RBD is quick to draw and easy to draw wrongly, and almost every wrong one is wrong before a single rate is entered. The sequence below front-loads the decisions that cannot be corrected later: what counts as success, where the system ends, and which failures the logic is allowed to survive.

1. State the success criterion, in a sentence

The criterion is the model. Everything else is bookkeeping. It is one sentence with three parts, agreed before anything is drawn: what the system must deliver, to what degree, for how long. The worked example uses "dry air above 6 bar at the actuator header, for 720 hours", and each clause changes the diagram: drop dry and the dryers leave the model, drop above 6 bar and one compressor is enough where two were needed, shorten the 720 hours and every redundant group looks better.

The criterion is silent aboutWhat goes wrong
The degree of service (full flow, degraded, minimum safe)A pair that is parallel at half load and series at full load gets drawn once, at the wrong load
The mission lengthRedundancy is scored at an unstated time, and every comparison between architectures becomes unfalsifiable
Which failures countThe diagram silently becomes a basic-reliability model, and redundancy stops paying
The starting stateA degraded start (one unit already out on a deferred defect) is the case the fleet actually flies, and it is a different diagram

A system with several criteria has several diagrams. That is not duplication, it is the honest answer: dispatch, mission success and safe shutdown are three different questions about one machine, and one drawing cannot hold all three.

2. Fix the boundary and the phase

The boundary decides what is a block and what is an assumption. Anything outside it is being assumed perfect, so the boundary list is a list of claims: mains power never fails, the operator always responds, the instrument air the other plant supplies is always there. Write them down; on a mature programme half of them turn out to be blocks.

Phased missions are handled by drawing one diagram per phase and multiplying, with two subtleties that catch people. A block that runs in only one phase accrues rate only in that phase. And a block that carried a phase and is still needed in the next one does not reset: its survival probability is conditional on having already survived what came before.

3. Draw the logic, not the schematic

The most common defective diagram is a redrawn P&ID or a redrawn wiring schematic. The test to apply to every branch is a question about function rather than about connection: if this block alone fails, does the system still meet the criterion? If yes, it is on a parallel path. If no, it is in series, however many pipes it has.

Physical arrangementReliability logic
Two pumps on two pipes, both needed at peak demandSeries
Two pumps on two pipes, either sufficient at the stated demandParallel
One cabinet containing two independent suppliesParallel
Three transmitters, any two of which must agree2-out-of-3
A cross-tie that only helps if it is open, and it is normally shutA block, and its own failure rate belongs on it

Two habits keep the drawing honest. Draw the support services (power, cooling, control air) as blocks the first time they are mentioned rather than the third. And give every block a rate source before moving on, because a block nobody can source is usually a block nobody has defined.

4. Populate the blocks

Rates arrive from the prediction, from FMECA at mode level, from life data, or from a vendor. Whichever the source, three declarations travel with the number and must match across the whole diagram: the unit (per 10⁶ hours, FIT, per demand), the clock (operating hours, calendar hours, cycles), and the mission time the block is exposed to, which is not the same for every block in a phased or partly duty-cycled system.

One conversion deserves care. A block whose failure is dormant, a standby unit or a protection channel, does not carry a rate over the mission in the same sense as a running one: its contribution is a probability of failure on demand, built from its dangerous-undetected rate and the interval since it was last proved. Putting a running rate on a dormant block is one of the few errors that makes a diagram optimistic by an order of magnitude.

5. Choose the evaluation

The structure isEvaluate by
Nested series and parallel groupsCollapsing block by block; every tool does this and so can a pencil
A voted groupThe k-out-of-n binomial on the branch reliability
A standby groupThe Poisson form, with the switch or start probability in it explicitly
A bridge or anything with a cross-connectionConditioning on the cross element, or enumeration
Large, and only a bound is neededThe minimal-cut lower bound, which is tight for systems that mostly work

6. Deal with what the blocks share

Shared causes against the answer. The compressor pair contributes 0.69 percentage points of unreliability when its failures are independent; at β = 0.10 the shared term alone contributes 0.86, and no further compressor touches it.
Shared causes against the answer. The compressor pair contributes 0.69 percentage points of unreliability when its failures are independent; at β = 0.10 the shared term alone contributes 0.86, and no further compressor touches it.

This is the step that separates a diagram that informs a decision from one that flatters it. Redundancy in a model is worth exactly as much as the independence behind it, and independence is an engineering claim about separation, not a mathematical convenience.

Apply the β-factor to every redundant group: a fraction β of each unit's rate is attributed to causes that take the group as a whole, and that shared portion is drawn as a block in series with the group. Then argue the value of β from the separation that actually exists.

Separation that existsWhat it does to β
Same design, same batch, same calibration, same roomβ at the pessimistic end; the pair is close to a single item for shared causes
Different manufacturer or different technologyDesign and manufacturing causes largely removed
Different location, different power source, different maintainerEnvironmental and human causes largely removed
Staggered maintenance, so the pair is never opened on the same dayRemoves the single most common human shared cause

Sensitivity beats precision here. Run the model at β = 0, 0.05 and 0.1 and report all three: if the decision changes between them, the number that needs work is β and not the block rates.

Two other shared-dependence cases have no β treatment. A support service is a real block and must be drawn. Load sharing, where the survivor works harder after the first failure, breaks the constant-rate assumption itself, and the group belongs in a state model.

7. Evaluate, and read the answer at the mission

The output is R(t) at the stated mission time. Two derived numbers are usually wanted with it, and both need a caveat attached:

  • The equivalent failure rate, λeq = −ln R(t) / t, which is the constant rate a series item would need to give the same result. It is a presentation device. It is valid at exactly the t it was computed at, and for a redundant system it changes with t.
  • The mean time to failure, ∫R(t)dt, which for a redundant structure is dominated by behaviour long after any mission of interest and can rank architectures in the opposite order to the mission result.

8. Rank what matters, not what fails most

An evaluated diagram gives a number; a ranked one gives a decision. Three rankings, answering three different questions:

RankingThe question it answers
Cut sets by order, then by probabilityWhich combinations actually carry the risk; an order-1 cut is a single point of failure whatever its rate
Birnbaum importance, ∂Rsys/∂RᵢHow much the system's reliability moves per unit of improvement in this block: where design effort pays
Criticality importance, IB · qᵢ / (1 − Rsys)Given that the system failed, how likely this block was responsible: where inspection and spares pay

The two importance measures disagree routinely and are both right. A single, very reliable block in series can have the highest Birnbaum importance in the model and a low criticality, because the system depends on it utterly and it almost never fails.

9. Test against the budget, then iterate

The diagram's result is compared with the mission budget the allocation set for this system, and the comparison has only four honest outcomes: it passes and the margin is recorded; it fails and the structure changes (a path added, a cut set broken, a shared cause separated); it fails and a block's rate must improve, which flows back to the design as a requirement; or it fails and the target is renegotiated on evidence. Redrawing the diagram until it passes is not on the list.

Then keep it alive. The structure is stable, the rates are not: a prediction re-run, a field failure, a change of supplier or a deferred-defect policy that lets the system dispatch with one path already down all move the answer, and the last of those changes the starting state the whole model assumed.


Want to see this on a live system model? Request a walkthrough.